Liander is responsible for providing a safe, reliable and affordable electricity grid. Every two years, the Municipality of Amsterdam and Liander assess how the demand for electricity is developing in the city. Based on this information, Liander indicates where potential bottlenecks may arise and where the electricity grid needs to be expanded.
The Municipality considers the use of space in the city and tests this against Amsterdam’s policy frameworks (spatial quality, greenery, water storage, etc.). If the electricity grid needs to be upgraded and/or expanded, in its capacity as initiator Liander asks for cooperation from the Municipality to make space available for this.
Liander and the Municipality work together closely, as the challenge in Amsterdam is sizeable, urgent and complex. You can see an overview of the responsibilities in the table below.
| Responsibilities of Liander as initiator | |
|---|---|
| Responsibilities of the Municipality of Amsterdam | |
|
|
Liander performs the tasks described in the Electricity Act and complies with legislation, regulations and municipal policy. Below you will find the rules that are most relevant for people living and working in the vicinity of the substation.
| Subject | |
|---|---|
| More information | |
| Electricity Act Ensuring electricity is transmitted in a safe and efficient manner. | |
| Environmental plan The upgrade fits in with the environmental plan. The ‘Weesperzijde strook’ land-use plan applies to the location. Irrevocable land-use plans form part of the environmental plan. The building is not being expanded, but upgraded, resulting in increased capacity. This is permitted within the current environmental plan. | |
| Surveys Liander will have various surveys conducted relating to soil, wildlife, water and the environment. | Examples:
|
| Permits Liander will apply for various permits for the demolition and construction of the substation and in relation to soil, wildlife, water and the environment. | Various permits
Legal procedures are in place for permit applications, which we will observe. We will tell you which permits we will need to apply for on the substation project page. Notification will be published on officielebekendmakingen.nl when a permit is granted. Once the permit has been granted it will be available for inspection for 6 weeks. You may raise an objection during this period. Liander will inform you when the environmental permit application is being submitted and when the permit is available for inspection. |
| Precautionary policy for magnetic fields Amsterdam precautionary policy for electromagnetic fields | |
| Policy document on planning regulations for the location and external appearance of buildings ‘De schoonheid van Amsterdam’ ('The beauty of Amsterdam') | |
| Protocol for electricity substations Protocol and process for the construction of substations, including participation paragraph.
|
| Phase of the project | |
|---|---|
| Degree of influence | |
| 2024: Location chosen by the Municipality | You were unable to exercise any influence over the choice of location. You are also unable to object to the site decision. The site decision is an administrative notification and means that the Municipality will cooperate with the procedures necessary to facilitate the upgrade and expansion of Rhijnspoor electricity substation at the designated location. |
| 2024-2025: Design phase |
|
| 2026-2027: Permit applications | Sometimes applications will need to be made for several permits for the construction or expansion of an electricity substation. Legal procedures apply here. On the project page for the substation we will tell you which permits will need to be applied for. You can object to the permits that Liander applies for. Once a permit has been granted it will be available for inspection for 6 weeks. You may raise an objection during this period. Liander will inform you when the environmental permit application is being submitted and when the permit is available for inspection. |
| 2027-2029: Work | During an information meeting that is yet to be scheduled, you will be able to make suggestions for measures that will help limit the disruption for the neighbourhood. |
We are always open to any questions or suggestions from local residents. You can contact us via:
E-mail: rhijnspoor@liander.nl
The BouwApp
For the Municipality, the need to upgrade the substation was seen as an opportunity to assess its location. The Municipality commissioned a study to determine whether there were other possible sites for the substation. The Municipal Executive then weighed up the options, based on wishes regarding the use of space, the costs, the associated inconvenience and safety-related aspects. The Municipal Executive has concluded that the current location is also the best site for the new substation. This has been documented in the site decision.
The new substation complies with the municipal precautionary policy (in Dutch) regarding magnetic fields and all legislation and regulations, including those covering noise. In its advice (in Dutch) the Municipal Health Service (GGD) indicates that there is no risk to health and the Municipality of Amsterdam therefore sees no reason to reconsider the location.
The choice of the current location for a new substation with increased capacity has raised questions amongst local residents concerning:
As the new electricity substation will be situated further away from the houses on Leeuwenhoekstraat, this will be beneficial in terms of light. As a result of amendments made to the design, we now know that the height will not be 16 metres, but approx. 13 metres (transformer building, left) and approx. 11 metres (switch building, right). This means that the building will cast less shadow. In the image below you can see the angle of elevation of the existing substation and the new situation. These images show the view from Deymanstraat.
In the neighbourhood survey people asked a lot of questions about magnetic fields. We have produced a comprehensive page (in Dutch) on this topic. You can read a summary of it below.
To limit magnetic fields, Liander is taking the following measures:
These ‘at-source measures’ are described (in Dutch) in this document (in Dutch).
At present, no homes fall within the 0.4 microtesla contour and this is also the case in the future situation. Consequently, the Rhijnspoor electricity substation complies with the precautionary policy of the Municipality of Amsterdam.
0.4 microtesla is the standard for places in which people spend long periods of time (approx. 14 – 18 hours per day), a definition comparable with housing.
The GGD therefore does not expect there to be any risks to the health of local residents due to the Rhijnspoor substation. You can read the advice of the GGD here (in Dutch).
The GGD can measure magnetic fields around the substation. It carried out such measurements at the end of 2024 at the request of local residents. At that time, values of up to 255 microtesla were measured on the outside wall of the building on Eerste Boerhaavestraat. This is above the standard of 100 microtesla for short-term exposure.
At a distance of 1 metre from the substation the strength decreased to 50 microtesla. On the outside walls of the homes the standard of 0.4 microtesla for long-term exposure was not exceeded.
The GGD does not expect there to be any health risks for local residents, but Liander is nevertheless taking measures to resolve the issue of the 100 microtesla standard being exceeded on the outside wall at Eerste Boerhaavestraat. We are currently looking into what these measures will be.
Once the new substation is in place, the GGD may perform further measurements.
A number of local residents asked what the Municipality will do if it becomes apparent that the EMF contour exceeds the standard. The Municipality cannot impose any measures on Liander.
The transformers and fans at the substation make a low humming noise. In the table below you can see a number of characteristics of the existing and new situation that have an impact on noise.
| Existing situation | ||
|---|---|---|
| New situation | ||
| Capacity | 64 MVA Three 50/10 kV transformers with a capacity of 32 MVA (megavolt amperes). Two transformers are on at all times. The third transformer serves as a backup. The available capacity is therefore 64 MVA.
|
106 MVA Three 150/10 kV transformers with a capacity of 53 MVA. Two transformers are on at all times. The third transformer serves as a backup. The available capacity is therefore 106 MVA. Transformers with a higher capacity generate more noise |
| Housing | Open The transformers are indoors and the fans are outdoors. | Closed. Both the transformers and the fans will be indoors. This will reduce noise. |
| Old versus new | Old | New |
|
Soundproofing | None | Thicker walls and soundproofing. The walls will be thicker and soundproofing will be installed in the ventilation ducts to further reduce noise. |
Liander is having a noise survey carried out by an independent agency to determine whether the substation complies with the rules. This will be verified by the Municipality of Amsterdam and the Environment Service.
If you suspect that noise standards are being exceeded and this is causing you inconvenience, you can report this to the Municipality via this link.The Municipality monitors companies that cause disruptive noise.
If this project leads to a demonstrable reduction in the value of your home, you can claim compensation for loss resulting from administrative acts. The loss in question must be greater than normal and affect you more than others.
Are you planning to sell your home? Avoid being liable for compensation after selling your home by informing the potential buyer before the sale about the plans to upgrade the substation. From discussions held in the local area we have learned that this was done when the newest properties on Leeuwenhoekstraat were sold. Information on the presence of the substation was included in the contract of sale for these properties.
The schedule of requirements is made up of Liander’s wishes and requirements and the Municipality of Amsterdam’s area planning framework. The area planning framework sets out the rules concerning the aesthetic quality, the desired spatial quality and other policies that apply to this site. This area planning framework has been coordinated with the COK (Environmental Quality Committee/Building Aesthetics Committee). We have also passed on to the architect the wishes expressed by local residents, which were gathered in 2024 during the information meeting and in the neighbourhood survey.
You can read more about the different levels for building aesthetics and what these mean on the Spatial Quality Committee’s website.
|
Greenery | |
|---|---|
|
Can the wish be incorporated in the design? | |
|
Green walls
|
No. The Municipality sets requirements for the design that fit in with the urban development plan. Green walls do not feature in this. For this reason green walls will not be included in the architect’s design brief. |
|
Green roofs
|
Yes. There will be greenery (sedum) on the roof of the new substation. |
|
Trees |
No. No trees will be planted on Liander’s site due to the underground cables. |
|
Greenery on the site |
Yes. The architect is investigating whether a hedge can be planted between the gardens of the houses on Leeuwenhoekstraat and the substation. We are looking into whether, in some places on the site, e.g. around the perimeter, we can use grass block paving (alternatively planted with sedum). |
|
Greening of the building on the Eerste Boerhaavestraat
|
We are investigating whether the structure of the building on Eerste Boerhaavestraat will allow for greenery (sedum) on the roof. |
|
Materials |
|
|
Pale bricks
|
Yes. The architect is investigating various (pale) colours and patterns for the walls and the fencing. |
| Reduction of particulates |
Yes. We are creating green (sedum) roofs, which help reduce particulates. Whether we can also utilise other materials to reduce particulates will become apparent in the course of the design process |
| Decorative pattern |
Yes. This is also one of the Municipality’s requirements |
|
Design |
|
| In keeping with the neighbourhood |
Yes. This is also one of the Municipality’s requirements |
| Open character, not a concrete colossus |
Yes. Part of the intended architectural effect is for the fencing to have an open and friendly character. |
|
Art
|
Liander is investigating together with the architect whether there are possibilities for this in the design. |
|
Solar panels
|
No. Liander has been asked by the Municipality to investigate the potential for green roofs. As we are not installing a combination of a green roof and solar panels, there will be no solar panels. . |
| Heat recovery |
No. The amount of heat released is limited and low in temperature. Furthermore, as a network operator, Liander is not permitted to sell heat. |
|
Site |
|
|
Water storage
|
Yes. We are examining both the current and future built surface area, as well as rainwater drainage and water storage on the site. We are investigating which measures can be taken to prevent flooding. Green roofs have been included in the design. In addition, we are investigating whether we can use grass block paving (alternatively planted with sedum) in a number of places, e.g. around the perimeter |
| Insect hotel |
We are investigating whether it would be possible to have one of these on the site |
|
Lighting
|
The site will not be permanently lit. Orientation lighting will only come on when a technician visits the substation, possibly combined with additional lighting to allow the work to be performed. |
| Bigger garden Leeuwenhoekstraat |
No. We are investigating whether, in addition to new fencing, a hedge could be planted between the gardens and the substation, on Liander’s site |
|
Safety of public space Lighting
|
Safety aspects are being considered as part of the design. To prevent break-ins, there will be no doors into the building on the street. By using open fencing and decorative elements in the brickwork, we will make the building less attractive for graffiti. We will discuss with the Municipality whether additional measures would be desirable in the public space to increase safety in the neighbourhood. Liander has nothing to do with the layout of the public space |
The scope for participation is very limited. The design for the substation must comply with:
We will do our best to incorporate as many wishes as possible of local residents into the design. Ultimately, Liander will choose the final design that will be used to apply for the permit.
Upgrading the substation will cause disruption. Large vehicles will be required and the demolition and building work may be noisy. Nevertheless, Liander will do everything possible to keep any inconvenience to a minimum.
In the neighbourhood survey people asked many questions relating to the work that will be carried out and possible disruption. We are not yet able to tell you what work will be carried out and when, and how this may affect you. As soon as we have a clearer picture of this we will let you know.
Generally speaking, we can say that: